Stage 1 (if recommended): Pre-Application (2-8+ weeks)
Before submitting an application, it can be worthwhile to seek pre-application advice from the Local Planning Authority (LPA), providing you with an opportunity to understand how the Council is likely to view your proposal before committing to a full application.
The timeframe varies significantly between Councils and depending on the complexity of the proposal. For example, a simple project may be relatively quick, whereas a larger or more complex development, it can take several months.
Whilst this does add some time onto the planning process, our advice is to not underestimate this stage, as a little more work before submission can sometimes save a lot of time in the long run!
Stage 2: Preparing the application (2–12+ weeks)
This is often the part of the process that some clients don’t always see.
A planning application isn’t just a form and a set of drawings. Depending on the proposal, it may require input from architects, highways specialists, ecologists, arboriculturalists, flood risk experts, landscape professionals, heritage specialists and other technical experts.
The amount of information required will depend on the scale, location and nature of the development.
This stage can therefore take anywhere from a couple of weeks to several months.
Stage 3: Submission and validation (around 1–4 weeks)
Once the application is submitted, the LPA will check that the necessary information has been provided. This is known as validation.
As with the Pre-Application process, the validation timeframe varies significantly between Councils!
If everything is in order, the application will be validated, and the determination period will begin. Alternatively, if information is missing, the Council may request further documents before validating the application.
This is one reason why getting the submission right the first time can make a real difference!
Stage 4: Consultation and determination (8–16 weeks)
Once validated, the application enters the formal determination process.
The Council may consult upon the following:
- Local residents;
- Parish or town councils;
- Highways authorities;
- Environmental bodies;
- Heritage consultees;
- Drainage authorities; and
- Other relevant statutory consultees.
The planning officer will then assess the proposal against relevant planning policies and other material considerations.
For many applications, this is where the statutory 8-week or 13-week period applies, however that doesn’t necessarily mean you’ll receive a decision exactly on the final day. Many applications can take longer where there are outstanding issues, objections, amended plans or negotiations with the Council.